Question No.41
What do project reports show during the Sprint review meeting?
-
Estimates compared to the baseline
-
Actual results to the plan
-
Return on investment (ROI)
-
Earned value measurement (EVM)
Correct Answer: C
Question No.42
Retrospectives provide an opportunity for the team to:
-
Reflect at the end of every iteration and identify improvements that will increase the quality of the product.
-
Participate in a mandatory meeting to share status updates across the team and to ensure that everyone is on track.
-
Understand from the management if the project is achieving the Scope, Quality, Cost, and Schedule goals.
-
Set goals at the beginning of the iteration and identify requirements that can be delivered in that iteration.
Correct Answer: A
Question No.43
When estimating initial velocity, the team should most likely:
-
Discuss among the team their expectations of how many story points they can address.
-
Use a Kanban workflow to identify steps and calculate velocity.
-
Use velocity of past iterations or make a calculated guess.
-
Discuss with the customer their expectation for the velocity of producing the product.
Correct Answer: C
Question No.44
In a Lean project environment, visual controls:
-
Can be used by management for communicating specific corrective direction.
-
Are easy to use, reflect the team#39;s progress, and show the team what to do next.
-
Are helpful while the team is forming but are less important for more experienced teams.
-
Should be kept to a minimum to avoid distracting the team from high-value activities.
Correct Answer: A
Question No.45
What is used to provide a simple medium for gathering basic information about stories, recording high-level requirements, developing work estimates, and defining acceptance tests?
-
Story card
-
Burndown chart
-
Retrospective
-
Storyboard
Correct Answer: A
Question No.46
During the daily standup meeting, a team member states that an issue has been encountered.This leads to the team members getting into a problem-solving discussion.How should the ScrumMaster respond?
-
Ask the team members to table the discussion until after the meeting is over.
-
If the item is really important, allow the discussion to expedite resolution of the issue.
-
Abruptly end the daily standup meeting and schedule another meeting to discuss the issue.
-
Ask the team how they would like to use the daily standup meeting for that day.
Correct Answer: A
Question No.47
What is one of the benefits of incremental delivery?
-
Value is delivered more quickly, as software can be released after every iteration.
-
More customers can be handled simultaneously, as each regularly receives a delivery.
-
Fewer bugs are introduced, as code is delivered to users more frequently.
-
Costs are reduced, as less verification is required to regression test each iteration.
Correct Answer: A
Question No.48
eXtreme Programming (XP) teams strive to avoid:
-
Incremental design and architecture.
-
Pair programming.
-
Manual regression testing.
-
Test-Driven Development (TDD).
Correct Answer: C
Question No.49
Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the
iteration and existing estimates were not changed.From this information, one can inferthat:
-
Work was removed from the Product Backlog.
-
Work was added to the Product Backlog.
-
The team#39;s velocity increased.
-
The team#39;s velocity decreased.
Correct Answer: B
Question No.50
What key benefits might stakeholders realize from an Agile approach?
-
The ability to bypass the change-management process, inserting new requirements and changes directly into the team as they meet daily
-
The early and continuous delivery of valuable software, providing increased visibility and the opportunity for more frequent adjustments
-
Increased access to the project and less reliance on formal reports and status meetings to better understand the current work and the risks the team is accepting
-
The team#39;s flexibility to make changes mid-iteration as business needs or priorities change, increasing the ability of the team to meet project commitments
Correct Answer: B