Question No.271

Which of the following documents describes the details for each component in the WBS?

  1. WBS detail

  2. Risk register

  3. WBS dictionary

  4. Project charter

Correct Answer: C

Question No.272

Which of the following risk response planning techniques is associated with threats and seeks to reduce the probability of occurrence, or impact of risk below an acceptable threshold?

  1. Risk avoidance

  2. Risk transference

  3. Risk mitigation

  4. Risk acceptance

Correct Answer: C

Question No.273

Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?

  1. Fallback plan

  2. Risk response plan

  3. Mitigation management plan

  4. Mitigation plan

Correct Answer: A

Question No.274

On which of the following documents you work throughout the risk management processes?

  1. Risk management plan

  2. Project management plan

  3. Risk register

  4. Project charter

Correct Answer: C

Question No.275

Small changes that bypass the organization#39;s change control procedures are called .

  1. Scope creep

  2. Lag

  3. Scope fault

  4. Gold plating

Correct Answer: A

Question No.276

All of the following information is defined in the program statement of work except for which one?

  1. Structure of the program management team

  2. Program requirements for resource competency levels

  3. Metrics and qualifications for program acceptance

  4. Location of the program work

Correct Answer: A

Question No.277

Which of the following documents is described in the statement below?

quot;It is a type of procurement document used to request proposals from prospective sellers of products or services.quot;

  1. Request for information

  2. Request for quote

  3. Request for proposal

  4. Request for bid

Correct Answer: C

Question No.278

What does RACI stand for?

  1. Responsible, Account, Confirm, Inform

  2. Responsible, Accountable, Consult, Inform

  3. Roles, Accountable, Confirm, Inform

  4. Roles, Action, Consult, Inform

Correct Answer: B

Question No.279

Which of the following is used to build consensus through rounds of anonymous surveys?

  1. The Pareto chart

  2. The Delphi technique

  3. The Monte Carlo simulation

  4. The Gantt chart

Correct Answer: B

Question No.280

The quality assurance technique ensures continuous improvement of all processes.

  1. Just-in-time management

  2. Ishikawa

  3. Six Sigma

  4. Kaizen

Correct Answer: D