Question No.91

There is a formal requirement from the business to develop an additional on-line application to the company website which will allow existing policyholders to extend their cover for short-term foreign use of their vehicle overseas. The current manual process will be retained. The application must be implemented in months time in line with the marketing department#39;s green initiative, which is anticipated to generate a significant increase in demand.

The development manager has insufficient resources to meet this request and has issued an invitation to potential bidders so that the development work can be outsourced.

The application must initially cover Western Europe, and later Eastern Europe, Russia, the Middle East, the Far East and Africa. A decision has yet to be made with respect to Australia, New Zealand, North and South America.

You have been asked to ensure the quality and suitability of the document sent to potential bidders and also that the application delivered by the successful bidder is `Tit for purpose#39;.

Which of the following product risks would be most effectively addressed just by static testing?

  1. In the delivered application, one of the countries, as specified in the requirements, has not been correctly implemented.

  2. The application takes too long to process a request for additional cover.

  3. The test cases do not cover the key requirements.

  4. The successful bidder may not deliver all the required functionality on time.

Correct Answer: C

Question No.92

There is a formal requirement from the business to develop an additional on-line application to the company website which will allow existing policyholders to extend their cover for short-term foreign use of their vehicle overseas. The current manual process will be retained. The application must be implemented in months time in line with the marketing department#39;s green initiative, which is anticipated to generate a significant increase in demand.

The development manager has insufficient resources to meet this request and has issued an invitation to potential bidders so that the development work can be outsourced.

The application must initially cover Western Europe, and later Eastern Europe, Russia, the Middle East, the Far East and Africa. A decision has yet to be made with respect to Australia, New Zealand, North and South America.

You have been asked to ensure the quality and suitability of the document sent to potential bidders and also that the application delivered by the successful bidder is `Tit for purpose#39;.

The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate?

  1. The bidder#39;s test policy should enforce that incident management fully conforms to IEEE 1044.

  2. The bidder#39;s project strategy shows that the data content of all the test environments conforms to EU standards.

  3. The bidder#39;s test plan shows that the application will be delivered for acceptance in six months time.

  4. The bidder#39;s project test plan depicts a phased implementation with later delivery dates to be confirmed and states that test deliverables will be developed using IEEE 829 as a guide.

Correct Answer: D

Question No.93

There is a formal requirement from the business to develop an additional on-line application to the company website which will allow existing policyholders to extend their cover for short-term foreign use of their vehicle overseas. The current manual process will be retained. The application must be implemented in months time in line with the marketing department#39;s green initiative, which is anticipated to generate a significant increase in demand.

The development manager has insufficient resources to meet this request and has issued an invitation to potential bidders so that the development work can be outsourced.

The application must initially cover Western Europe, and later Eastern Europe, Russia, the Middle

East, the Far East and Africa. A decision has yet to be made with respect to Australia, New Zealand, North and South America.

You have been asked to ensure the quality and suitability of the document sent to potential bidders and also that the application delivered by the successful bidder is `Tit for purpose#39;. The following Test Cases have been created for a simple web-based airline booking system. Test Case 1: Search for an item: Available Flights

Test Case 2: View selected item in My Flights

Test Case 3: Login to the system: Login is accepted

Test Case 4: Select an available flight: item added to My Flights Test Case 5: Print confirmation receipt, then exit

Test Case 6: In My Flights, confirm details and book flight

Which of the following is the correct logical order for the test cases?

A.

6, 3, 1, 4, 2, 5

B.

3, 4, 1, 2, 5, 6

C.

3, 2, 1, 4, 6, 5

D.

3, 1, 4, 2, 6, 5

Correct Answer: B

Question No.94

There is a formal requirement from the business to develop an additional on-line application to the company website which will allow existing policyholders to extend their cover for short-term foreign use of their vehicle overseas. The current manual process will be retained. The application must be implemented in months time in line with the marketing department#39;s green initiative, which is anticipated to generate a significant increase in demand.

The development manager has insufficient resources to meet this request and has issued an invitation to potential bidders so that the development work can be outsourced.

The application must initially cover Western Europe, and later Eastern Europe, Russia, the Middle East, the Far East and Africa. A decision has yet to be made with respect to Australia, New Zealand, North and South America.

You have been asked to ensure the quality and suitability of the document sent to potential bidders and also that the application delivered by the successful bidder is `Tit for purpose#39;.

Your task is to compile a test execution schedule for the current release of software. The system specification states the following logical dependencies:

An admin user must create/amend/delete a standard user. A standard user is necessary to perform all other actions.

The test plan requires that re-tests must be performed first, followed by the highest priority tests. To save time, the test plan states that tests should be scheduled to create test data for the subsequent tests in the schedule.

The following test cases have been designed, with an indication of priority (1 being the highest priority) and whether the test has previously failed.

image

Which test execution schedule meets the test plan requirements and logical dependencies?

  1. a, d, c, b, e

  2. a, c, b, d, e

  3. e, a, b, c, d

  4. e, a, d, c, b

Correct Answer: C

Question No.95

While waiting for the responses, the test manager has been asked to prepare test plans to validate the software application delivered by the successful bidder. Which one of the following estimation approaches is appropriate at this stage of the project?

  1. Create an estimate based on the function point analysis technique and test point analysis

  2. Create an estimate based on the complexity of the code

  3. Create an estimate based on the credentials of the successful bidder

  4. Create an estimate based on a percentage of the development effort

Correct Answer: A

Question No.96

The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid Application Development (RAO) approach. Why might a RAD approach be a better option for the test manager rather than a sequential development?

  1. It will extend the development team#39;s abilities and enhance future delivery capabilities.

  2. It will allow the marketing, clerical and testing staff to validate and verify the early screen prototypes.

  3. Time-box constraints will guarantee code releases are delivered on schedule.

  4. More time can be spent on test execution as less formal documentation is required.

Correct Answer: B

Question No.97

The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid Application Development (RAO) approach. Which of the following is NOT a typical key challenge for testing in a RAD based development approach?

  1. Re-usable test scripts for (automated) regression testing

  2. Project management and control

  3. No complete requirements specification

  4. Time-boxing

Correct Answer: B

Question No.98

The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid Application Development (RAO) approach. As a result of the RAD based development approach, the test manager has decided to change the risk mitigation approach. Which test technique might be most appropriate to use?

  1. Decision Table Testing

  2. Boundary Value Analysis

  3. Error Guessing

  4. Exploratory Testing

Correct Answer: D

Question No.99

The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid Application Development (RAO) approach. The business has asked for a weekly progress report. Which of the following would be appropriate as a measure of test coverage?

  1. Percentage of business requirements exercised

  2. Percentage of planned hours worked this week

  3. Percentage of countries that have test scenarios

  4. Percentage of test iterations completed

Correct Answer: A

Question No.100

The following is the current incident handling process in used at the company. Step 1: Incident is documented in the incident Tile with the following information: Software module or area where the fault occurred

Who has reported the fault

Hardware configuration used for the test that found the fault

The sequential incident number (1 greater than the last one recorded)

Step 2: Developer assigned to fix the fault Step 3: Developer fixes the fault

Step 4: Developer signs off the incident as closed, and it is then removed from the incident file

Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide?

  1. No priority or severity assigned

  2. Incident numbering is manual rather than automated

  3. No mentioning of reproduceability

  4. No classification on type of incident

Correct Answer: A