Question No: 81 – (Topic 1)

A project has been running for four months. The planned value to this point is $100,000. The actual cost is an average of $30,000 per month. Earned value is $90,000. Which of the

following is the current cost performance index?

A. 0.75

B. 1.25

  1. $20,000 over budget

  2. Not enough detail to determine

Answer: A

Question No: 82 – (Topic 1)

A team member approaches the project manager and is concerned that the project is running behind and is overspending. Which of the following tools would the project manager use to validate the team member’s concern? (Select TWO).

  1. CPI

  2. AC

  3. EV

  4. PV

  5. SV

  6. BAC

Answer: A,E

Question No: 83 – (Topic 1)

Determining how to communicate general project information with a globally dispersed team has created scheduling challenges. Which of the following would BEST remedy the situation?

  1. Provide a written forum that allows for asynchronous participation

  2. Conduct a meeting at a time where everyone is inconvenienced

  3. Schedule a meeting when the majority of the team is available

  4. Establish a conference call with all team members

Answer: A

Question No: 84 – (Topic 1)

Once a project manager has been assigned, which of the following would the project manager do NEXT?

  1. Develop task assignments

  2. Finalize the project charter

  3. Draft a communications plan

  4. Conduct risk analysis

Answer: B

Question No: 85 – (Topic 1)

A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule?

  1. SPI = 0.89, ahead of schedule

  2. SPI = 0.90, behind schedule

  3. SPI = 1.11, behind schedule

  4. SPI = 1.20, ahead of schedule

Answer: D

Question No: 86 – (Topic 1)

Which of the following components of the project charter is used to help determine the project’s communication needs?

  1. Stakeholder identification

  2. Project objectives

  3. Problem statement

  4. Key deliverables

Answer: A

Question No: 87 – (Topic 1)

Which of the following is a document used iteratively during a project to capture strengths and weaknesses?

  1. Quality plan

  2. Scope document

  3. Lessons learned

  4. Business impact analysis

Answer: C

Question No: 88 – (Topic 1)

When a project manager creates a communication plan, which of the following should be included? (Select TWO).

  1. Project communication formats

  2. Financials

  3. Red, yellow, and green project status

  4. Escalation path

  5. Overview of the project

  6. Risks and issues

Answer: A,D

Question No: 89 – (Topic 1)

The project is half way through the schedule and the steering committee has approved a change request to add additional functionality to the program. The project manager’s NEXT step is to:

  1. crash the schedule.

  2. do an impact analysis.

  3. look for ways to save money.

  4. update the project plan.

Answer: D

Question No: 90 – (Topic 1)

Which of the following is the project manager implementing when allocating additional resources to a set of tasks that are in the critical path and are slowing down the project completion?

  1. Crashing

  2. Optimizing

  3. Controlling

  4. Fast tracking

Answer: A

100% Dumps4cert Free Download!
PK0-003 PDF
100% Dumps4cert Pass Guaranteed!
PK0-003 Dumps

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

You must be logged in to post a comment.

Proudly powered by WordPress   Premium Style Theme by www.gopiplus.com