Question No: 51 – (Topic 1)
Which of the following areas is addressed in the Project Charter?
-
Project team members
-
Work Breakdown Structure (WBS)
-
Business needs
-
Communications venue
Answer: C
Question No: 52 – (Topic 1)
A project baseline should be captured when the:
-
project manager is satisfied with the project tasks and risks associated.
-
sponsor is ready for work to begin and conducts a kick-off meeting.
-
schedule is fully developed with activity names, durations, dependencies, and costs.
-
WBS and WBS dictionary have been defined and agreed upon.
Answer: C
Question No: 53 – (Topic 1)
Which of the following shows how often contracts would be closed for the procurements on a project?
-
During phase gate review
-
After the project is completed
-
At the end of the project
-
At the end of the contract
Answer: D
Question No: 54 – (Topic 1)
Given the following:
-
Senior management support will maintain throughout the duration of the project.
-
Technical hardware onsite is sufficient to support the new application.
-
Network connectivity is able to support the new product.
-
All scope changes will follow the change control process.
Which of the following components of a scope document would BEST capture the above criteria?
-
Assumptions
-
Constraints
-
Key performance indicators
-
Objectives
-
-
Answer: A
Question No: 55 – (Topic 1)
It is the first week after a project kick-off. The project team is not making much progress on decisions needed and are disagreeing with each other. Which of the following represents the team#39;s current stage?
-
Storming
-
Norming
-
Forming
-
Performing
Answer: A
Question No: 56 – (Topic 1)
A stakeholder wants to add another requirement to the deliverable. Which of the following will the project manager do to determine the change’s effect on the project?
-
Performing an impact analysis
-
Identifying a change
-
Coordinating with stakeholders to select the course of action
-
Filling out a change control
Answer: A
Question No: 57 – (Topic 1)
Which of the following describes the total amount of money approved for spending on a project?
-
VAC
-
BAC
-
ETC
-
EAC
Answer: B
Question No: 58 – (Topic 1)
Which of the following is a component of a performance evaluation for an individual?
-
Resource utilization
-
Role assessment
-
Scope management
-
Variance management
Answer: B
Question No: 59 – (Topic 1)
The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?
-
Cost performance index
-
Risk mitigation
-
Schedule variance
-
Cost variance
Answer: C
Question No: 60 – (Topic 1)
A well-written scope document will include which of the following? (Select TWO).
-
Contact information
-
Milestones
-
Stakeholders
-
Constraints
-
Project acceptance criteria
-
Project tasks
Answer: D,E
100% Dumps4cert Free Download!
–PK0-003 PDF
100% Dumps4cert Pass Guaranteed!
–PK0-003 Dumps
Dumps4cert | ExamCollection | Testking | |
---|---|---|---|
Lowest Price Guarantee | Yes | No | No |
Up-to-Dated | Yes | No | No |
Real Questions | Yes | No | No |
Explanation | Yes | No | No |
PDF VCE | Yes | No | No |
Free VCE Simulator | Yes | No | No |
Instant Download | Yes | No | No |