Question No: 131 – (Topic 2)
While closing out phases and the project, the project manager collects information about what went well, what can be improved, what could have been done differently, and what should be retained and reused. This is MOST commonly documented in the:
-
lessons learned.
-
transition plan.
-
procurement audit.
-
project report.
Answer: A
Question No: 132 – (Topic 2)
A defect in an application code is observed and documented in the middle of a project. The defect is noted as a security risk and requires immediate action. Who is responsible for approving the required fix?
-
Contracting officer
-
Lead developer
-
Change control board
-
Risk management team
Answer: C
Question No: 133 – (Topic 2)
Which of the following includes validating the project charter and introducing key members of the team?
-
Kick-off meeting
-
Stakeholder register
-
Team-building event
-
Communications plan
Answer: A
Question No: 134 – (Topic 2)
A project manager is in the process of developing a charter. The project manager is concerned about communicating with affected business groups. Which of the following needs to be done to ensure all necessary parties are engaged in the effort?
-
Reviewing the work breakdown structure
-
Identifying the stakeholders
-
Developing the project baseline
-
Drafting the change management plan
Answer: B
Question No: 135 – (Topic 2)
Which of the following represents the difference between the planned budget and the final cost to complete the project?
-
ETC
-
BAC
-
EAC
-
VAC
Answer: D
Question No: 136 – (Topic 2)
Which of the following conflict management techniques is represented by making concessions to maintain team harmony?
-
Smoothing
-
Negotiating
-
Collaborating
-
Avoiding
Answer: A
Question No: 137 – (Topic 2)
Which of the following contract types would MOST likely be used in a project that has a well-defined scope and a strong change control process in place?
-
Cost plus incentive
-
Firm fixed cost
-
Cost reimbursable
-
Time and materials
Answer: B
Question No: 138 – (Topic 2)
Although a needed item can be made in-house, it has been determined that it will be procured. Since the scope is well-defined, which of the following procurement documents should be used and which contract type should result?
-
Request for proposal, and cost plus contract
-
Request for quote, and time and material contract
-
Request for bid, and fixed price contract
-
Request for information, and unit price contract
Answer: C
Question No: 139 – (Topic 2)
A project manager is concerned that the project schedule will extend beyond initial estimation. Which of the following methods will allow the project manager to determine the project duration with the MOST precision?
-
Gantt
-
CCM
-
CPM
-
PERT
Answer: C
Question No: 140 – (Topic 2)
Which of the following would be the BEST document for determining project resourcing needs?
-
Scope statement
-
Work breakdown structure
-
Project charter
-
Quality plan
Answer: B
100% Dumps4cert Free Download!
–PK0-003 PDF
100% Dumps4cert Pass Guaranteed!
–PK0-003 Dumps
Dumps4cert | ExamCollection | Testking | |
---|---|---|---|
Lowest Price Guarantee | Yes | No | No |
Up-to-Dated | Yes | No | No |
Real Questions | Yes | No | No |
Explanation | Yes | No | No |
PDF VCE | Yes | No | No |
Free VCE Simulator | Yes | No | No |
Instant Download | Yes | No | No |