Question No: 241 – (Topic 3)
Which of the following documents would be generated to solicit bids from outside vendors?
-
WBS
-
PERT
-
RFP
-
SOW
Answer: C
Question No: 242 – (Topic 3)
Which of the following conclusions can be drawn when a project has a CPI of 1.2?
-
The project is taking longer than the estimated schedule.
-
The project is costing less than the estimated budget.
-
The project is taking less time than the estimated schedule.
-
The project is costing more than the estimated budget.
Answer: B
Question No: 243 – (Topic 3)
Which of the following represents the EAC of an ongoing project with an AC of $100,000, a CV of $10,000 and an ETC of $50,000?
A. $90,000 B. $140,000 C. $150,000 D. $160,000
-
The project is taking longer than the estimated schedule.
-
The project is costing less than the estimated budget.
-
The project is taking less time than the estimated schedule.
-
The project is costing more than the estimated budget.
Answer: C
Question No: 244 – (Topic 3)
Which of the following resource leveling techniques describes schedule compression by performing activities concurrently?
-
Exploiting
-
Crashing
-
Optimizing
-
Fast tracking
Answer: D
Question No: 245 – (Topic 3)
Which of the following describes a quality control tool used to analyze defects based upon number of occurrences?
-
Pareto diagram
-
Scatter diagram
-
Fishbone diagram
-
Ishikawa diagram
Answer: A
Question No: 246 – (Topic 3)
Which of the following is an important aspect of formal project closure?
-
Assign resources to the next project.
-
Analyze quality and ensure standards are being met.
-
Document lessons learned for use in future projects.
-
Modify the WBS to include all the change requests that occurred during the project.
Answer: C
Question No: 247 – (Topic 3)
Which of the following would be the BEST tool to estimate activity time durations?
-
Gantt chart
-
CPM
-
Estimating model
-
PERT
Answer: D
Question No: 248 – (Topic 3)
Who has the MOST control over project scope changes?
-
Key stakeholders
-
Project sponsor
-
Project manager
-
Change control board
Answer: D
Question No: 249 – (Topic 3)
Monitoring and controlling project work is a control process function that spans from:
-
the creation of the project work plan to the completion of the work breakdown structure (WBS).
-
project kickoff to the project completion, including documentation of lessons learned.
-
project kickoff to the project plan generation.
-
the creation of the project work plan to the completion of the statement of work (SOW)
Answer: B
Question No: 250 – (Topic 3)
A project has been cancelled during the execution phase. Which of the following steps should be taken?
-
Continue to work the project.
-
Finish the project charter and project plan.
-
Complete lessons learned document.
-
Develop the project transition plan.
Answer: C
100% Dumps4cert Free Download!
–JK0-017 PDF
100% Dumps4cert Pass Guaranteed!
–JK0-017 Dumps
Dumps4cert | ExamCollection | Testking | |
---|---|---|---|
Lowest Price Guarantee | Yes | No | No |
Up-to-Dated | Yes | No | No |
Real Questions | Yes | No | No |
Explanation | Yes | No | No |
PDF VCE | Yes | No | No |
Free VCE Simulator | Yes | No | No |
Instant Download | Yes | No | No |