Question No: 221 – (Topic 3)

At a project milestone meeting, the project sponsor asked about a deliverable that is not on the project plan. Which of the following should the project manager do to compensate for this unmet expectation?

  1. Review the scope with the vendor.

  2. Review the scope with the customer.

  3. Review the scope with the team.

  4. Review the scope with the sponsor.

Answer: D

Question No: 222 – (Topic 3)

The project scope document should outline which of the following project items? (Select Two).

  1. Services

  2. Lessons learned

  3. Products

  4. Schedule baselines

  5. Resource availability

Answer: A,C

Question No: 223 – (Topic 3)

Which of the following is an input to a work breakdown structure (WBS)?

  1. Performance reports

  2. Stakeholder analysis

  3. Project scope statement

  4. Variance analysis

Answer: C

Question No: 224 – (Topic 3)

Which of the following should be included in a Gantt chart to analyze a project schedule? (Select Three).

  1. Risks

  2. Probability

  3. Cost analysis

  4. Start date

  5. Activity durations

  6. Finish date

Answer: D,E,F

Question No: 225 – (Topic 3)

Which of the following can a project manager use to determine the critical path of a project? (Select Three).

  1. Business requirements

  2. Sequence of activities

  3. Completion date

  4. Stakeholder expectations

  5. Start date

  6. Risk register

Answer: B,C,E

Question No: 226 – (Topic 3)

Which of the following will have the GREATEST impact upon the outcome of a project? (Select Two).

  1. Quality metrics

  2. Scope creep

  3. Performance reports

  4. Project life cycle

  5. Project delays

Answer: B,E

Question No: 227 – (Topic 3)

A stakeholder asks the project manager to finish a project early. The project manager should ask the stakeholder to FIRST:

  1. speak to the other stakeholders to get their opinion.

  2. complete a change request form.

  3. speak to the project sponsor.

  4. consider how this might impact the quality of the product.

Answer: B

Question No: 228 – (Topic 3)

The communication plan for a project is a subset of which of the following documents?

  1. Project charter

  2. Risk management plan

  3. Project schedule

  4. Project plan

Answer: D

Question No: 229 – (Topic 3)

Whose approval should be obtained before modifying the scope of a project?

  1. Project team

  2. Executive management team

  3. Change control board

  4. Stakeholders

Answer: C

Question No: 230 – (Topic 3)

Which of the following are schedule compression techniques? (Select Two).

  1. Fast tracking

  2. Critical Path Method (CPM)

  3. Crashing

  4. PERT analysis

  5. Schedule network analysis

Answer: A,C

100% Dumps4cert Free Download!
JK0-017 PDF
100% Dumps4cert Pass Guaranteed!
JK0-017 Dumps

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

You must be logged in to post a comment.

Proudly powered by WordPress   Premium Style Theme by www.gopiplus.com