CompTIA E2C Project Certification Exam

Question No: 21 – (Topic 1)

Which of the following represents the appropriate order of an effective change management process?

  1. Identify change, perform impact analysis, approve or deny change, update applicable project plan components, document change.

  2. Identify change, document change, perform impact analysis, approve or deny change, update applicable project plan components.

  3. Identify change, document change, perform impact analysis, update applicable project plan components, approve or deny change.

  4. Identify change, document change, approve or deny change, perform impact analysis, update applicable project plan components.

Answer: B

Question No: 22 – (Topic 1)

Which of the following conflict resolution techniques is used to get people to face their conflicts directly and work through the issues?

  1. Confronting

  2. Forcing

  3. Compromising

  4. Smoothing

Answer: A

Question No: 23 – (Topic 1)

In which of the following organization types would a project manager have the MOST authority?

  1. Projectized

  2. Balanced Matrix

  3. Weak Matrix

  4. Functional

Answer: A

Question No: 24 – (Topic 1)

Which of the following would be a direct output of the initiating process group? (Select Two).

  1. Project charter

  2. Project management plan

  3. Statement of Work (SOW)

  4. Work Breakdown Structure (WBS)

  5. Preliminary scope statement

Answer: A,E

Question No: 25 – (Topic 1)

Which of the following cost estimating techniques uses previous, similar projects as a basis of estimating costs for the current project?

  1. Top-down estimating

  2. Parametric estimating

  3. Bottom-up estimating

  4. Analogous estimating

Answer: D

Question No: 26 – (Topic 1)

Which of the following tools are used for quality planning? (Select Two).

  1. Cost / Benefit analysis

  2. Network diagram

  3. Benchmarking

  4. Critical Path Method (CPM)

  5. Parametric estimating

Answer: A,C

Question No: 27 – (Topic 1)

Which of the following is a use for a Pareto diagram?

  1. In procurement management to evaluate vendor proposals.

  2. In cost management to determine actual versus expected project costs.

  3. In quality management to identify and prioritize problem areas.

  4. In risk management to assess potential project risk occurrences.

Answer: C

Question No: 28 – (Topic 1)

Which of the following quality control tools illustrates the various factors that may be linked to potential problems or effects?

  1. Ishikawa diagram

  2. Histogram

  3. Run chart

  4. Scatter diagram

Answer: A

Question No: 29 – (Topic 1)

Which of the following risk response strategies involves shifting the negative impact of a threat, along with ownership of the response, to a third party?

  1. Risk transfer

  2. Risk avoidance

  3. Risk sharing

  4. Risk mitigation

Answer: A

Question No: 30 – (Topic 1)

Which of the following risk response strategies involves the use of insurance, performance bonds, or warranties?

  1. Risk acceptance

  2. Risk mitigation

  3. Risk avoidance

  4. Risk transfer

Answer: D

100% Dumps4cert Free Download!
JK0-017 PDF
100% Dumps4cert Pass Guaranteed!
JK0-017 Dumps

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No