CompTIA E2C Project Certification Exam
Question No: 171 – (Topic 2)
The change control board approved a request for $25,000 to address rising labor costs of specialized trades. Which of the following documents should be updated?
-
Scope statement
-
Project schedule
-
Resource requirements
-
Project budget
Answer: D
Question No: 172 – (Topic 2)
Refer to the attached Exhibit.
Which of the following is the duration of the critical path in the diagram?
-
2
-
5
-
6
-
7
Answer: D
Question No: 173 – (Topic 2)
The frequency of measurement would be found in which of the following documents?
-
Risk management plan
-
Scope management plan
-
Quality management plan
-
Communication management plan
Answer: C
Question No: 174 – (Topic 2)
The project has been terminated prematurely by the organization. Which of the following will the project manager need to complete?
-
Case study
-
Cost benefit analysis
-
Quality assessment
-
Post-mortem
Answer: D
Question No: 175 – (Topic 2)
A project manager has finished the first phase of a project. Who of the following determines if the project continues?
-
End users
-
Project manager
-
Project team
-
Project sponsor
Answer: D
Question No: 176 – (Topic 2)
The project has an AC of $5,000. Which of the following would be used to determine the budget needed to complete the project?
-
ETC
-
PV
-
BAC
-
EAC
Answer: A
Question No: 177 – (Topic 2)
Which of the following skills would be the MOST useful in assembling an effective project team in a functional organization?
-
Compromising
-
Negotiation
-
Estimating
-
Padding
Answer: B
Question No: 178 – (Topic 2)
A project manager has been assigned two team members who do not get along. On past projects they have proven very difficult to work with and are often at odds with one another. Which of the following conflict resolution techniques would be BEST to address this?
-
Forcing
-
Avoiding
-
Confronting
-
Compromising
Answer: C
Question No: 179 – (Topic 2)
A project manager is receiving many requests for changes to a project. Which of the following did the project manager fail to complete?
-
Proper project team selection
-
Subject Matter Expert (SME) solicitation
-
Milestone scheduling
-
Stakeholder analysis
Answer: D
Question No: 180 – (Topic 2)
A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the following BEST describes the technique the project manager is using?
-
Schedule optimization
-
Fast tracking
-
Resource management
-
Crashing
Answer: D
100% Dumps4cert Free Download!
–JK0-017 PDF
100% Dumps4cert Pass Guaranteed!
–JK0-017 Dumps
Dumps4cert | ExamCollection | Testking | |
---|---|---|---|
Lowest Price Guarantee | Yes | No | No |
Up-to-Dated | Yes | No | No |
Real Questions | Yes | No | No |
Explanation | Yes | No | No |
PDF VCE | Yes | No | No |
Free VCE Simulator | Yes | No | No |
Instant Download | Yes | No | No |