CompTIA E2C Project Certification Exam

Question No: 131 – (Topic 2)

A key stakeholder on a project advises the project manager that there is a component of the project that has yet to be decided. They are concerned that their needs regarding this component will not be addressed. In which of the following documents should the project manager record this information?

  1. Lessons learned

  2. Issue log

  3. Statement of Work (SOW)

  4. Project charter

Answer: B

Question No: 132 – (Topic 2)

A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is

$990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?

  1. Estimate to completion

  2. Planned value

  3. Cost performance index

  4. Budget at completion

Answer: B

Question No: 133 – (Topic 2)

The amount of time ahead or behind schedule on a project is called the:

  1. schedule baseline.

  2. schedule performance index.

  3. estimate to complete.

  4. schedule variance.

Answer: D

Question No: 134 – (Topic 2)

A project sponsor is adamant that a complex project must be completed within 12 months. Based on lessons learned from previous projects of this type, the project manager believes that the project cannot possibly finish in less than 24 months. Which of the following tools can the project manager use to show the improbability of the proposed timeline?

  1. Pareto Diagram

  2. Decision tree

  3. Monte Carlo analysis

  4. Quantitative risk analysis

Answer: C

Question No: 135 – (Topic 2)

A network diagram shows two critical paths for a project. Which of the following will MOST likely increase?

  1. Staff

  2. Risk

  3. Cost

  4. Time

Answer: B

Question No: 136 – (Topic 2)

A project manager is responsible for meeting with the companys project review board to periodically evaluate the progress on a project. Which of the following is the role of the board?

  1. To supply audit trail oversight

  2. To ensure local standards compliance

  3. To provide decision oversight

  4. To communicate to stakeholders

Answer: C

Question No: 137 – (Topic 2)

Which of the following are components of an internal / external communication plan? (Select Two).

  1. Technology requirements

  2. Communication budget

  3. Distribution list

  4. Stakeholders list

  5. Communication frequency

Answer: C,E

Question No: 138 – (Topic 2)

A project manager creates a detailed list of costs for each activity involved in the project and then uses the sum of the individual activities to create the budget. Which of the following cost estimating techniques was used?

  1. Bottom-up

  2. Expert judgment

  3. Parametric

  4. Top-down

Answer: A

Question No: 139 – (Topic 2)

Communication preferences, cultural differences, and language barriers are BEST described as which of the following?

  1. Special communication needs of project members

  2. Critical aspects of managing stakeholder expectations

  3. Items within the risk management plan

  4. Reasons for premature project failure / abandonment

Answer: A

Question No: 140 – (Topic 2)

A healthcare company must store project records for seven years. This is an example of which of the following?

  1. Document retention compliance

  2. ISO compliance

  3. Version control compliance

  4. Document version control

Answer: A

100% Ensurepass Free Download!
Download Free Demo:JK0-017 Demo PDF
100% Ensurepass Free Guaranteed!
Download 2018 EnsurePass JK0-017 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

You must be logged in to post a comment.

Proudly powered by WordPress   Premium Style Theme by www.gopiplus.com